Ditch 6A - From May 8 to June 11, 2025 - The crews sprayed herbicide on these ditches only, and great care was taken to complete the task.
Ditch 6A and 6B - From June 12 to July 10, 2025 - Our crews mowed this ditch, and no unusual occurrences taking place.
For the month of August and September - Ditch 6 was mowed. The crew went back at another time in the month of September to slope mow the ditches.
Once again, on September 15, 2025, the crew of GCDD2 mowed and spayed this ditch. This was done well by our crew, with great efficiency to complete the task.